BID PACKAGE SCHEDULE

Subcontractors shall be properly authorized to conduct business in the State of Nevada and Clark County, be licensed by the Nevada State Contractors Board pursuant to NRS Chapter 624, holding the proper subcategory of license for the work under NAC Chapter 624, and have a sufficient financial limit on their license of at least 125% of the estimate amount, prior to providing a response to any Request for Proposals. No proposals will be accepted from any company not meeting these requirements.

Access to the bid documents will be granted after execution of a Non-Disclosure Agreement (NDA).  Any bid solicitations that do not originate from Building Connected or charge a fee for access to the project documents are not from the Mortenson | McCarthy Joint Venture.

BP#
Scopes
Issued
Due
1.01
Cable Net Glazing - DA Partner
04/26/2024
06/06/2024
2a.01
Structural Steel - Designer Assist (DA) Partner
08/26/2024
09/26/2024
2a.02
Fire Protection - DA Partner
08/26/2024
09/26/2024
2a.03
Plumbing - DA Partner
08/26/2024
09/26/2024
2a.04
Mechanical/Controls - DA Partner
08/26/2024
09/26/2024
2a.05
Electrical - DA Partner
08/26/2024
09/26/2024
2b.06
Metal Roofing - DA Partner
08/26/2024
10/01/2024
2b.07
Curtain Wall (including storefront / ext glass doors) - DA Partner
08/26/2024
10/01/2024
2b.08
ETFE - DA Parter
08/26/2024
10/01/2024
2b.09
Vertical Transportation - DA Partner
08/26/2024
10/01/2024
3.01
Structural Precast
10/18/2024
11/14/2024
3.02
Low Voltage
10/18/2024
11/14/2024
4.01
Civil / Utilities
03/03/2025
03/25/2025
4.02
Deep Foundations
03/03/2025
03/25/2025
4.03
Concrete
03/03/2025
03/25/2025
4.04
Misc Metals - Stairs Only
03/03/2025
03/25/2025
4.05
Expansion Control
03/03/2025
03/25/2025
4.06
Water Proofing / Damp Proofing
03/03/2025
03/25/2025
4.07
Exterior Metal Panels / Exterior Studs / Framing / Air Barrier / Exterior Blocking
03/03/2025
03/25/2025
4.08
Masonry
03/03/2025
03/25/2025
4.09
Interior Drywall / Framing
03/03/2025
03/25/2025
4.10
Stadium Railings
03/03/2025
03/25/2025
4.11
Fire Proofing
03/03/2025
03/25/2025
4.12
Video Boards
03/03/2025
03/25/2025
5.01
Playing Field / Turf Contract
01/05/2026
02/06/2026
5.02
Misc Metals
01/05/2026
02/06/2026
5.03
Interior Rough Carpentry
01/05/2026
02/06/2026
5.04
Architectural Casework
01/05/2026
02/06/2026
5.05
Lockers
01/05/2026
02/06/2026
5.06
Interior Metal Panels
01/05/2026
02/06/2026
5.07
Doors, Frames & Hardware
01/05/2026
02/06/2026
5.08
Overhead Doors
01/05/2026
02/06/2026
5.09
Coiling smoke doors
01/05/2026
02/06/2026
5.10
Interior Storefront & Glazing
01/05/2026
02/06/2026
5.11
Tile
01/05/2026
02/06/2026
5.12
Acoustical Ceilings
01/05/2026
02/06/2026
5.13
Carpet and Resilient Flooring
01/05/2026
02/06/2026
5.14
Polished Concrete
01/05/2026
02/06/2026
5.15
Epoxy Flooring
01/05/2026
02/06/2026
5.16
Acoustical Treatments
01/05/2026
02/06/2026
5.17
Painting and Wall Covering
01/05/2026
02/06/2026
5.18
Toilet Compartments
01/05/2026
02/06/2026
5.19
Wall Protection
01/05/2026
02/06/2026
5.20
Access Flooring
01/05/2026
02/06/2026
5.21
Signage (wayfinding / code)
01/05/2026
02/06/2026
5.22
Fire Protection Specialties
01/05/2026
02/06/2026
5.23
Operable Partitions
01/05/2026
02/06/2026
5.24
Toilet Accessories
01/05/2026
02/06/2026
5.25
Maintenance Equipment
01/05/2026
02/06/2026
5.26
Laundry Equipment
01/05/2026
02/06/2026
5.27
Loading Dock Equipment
01/05/2026
02/06/2026
5.28
Food Service Equipment
01/05/2026
02/06/2026
5.29
Residential Appliances
01/05/2026
02/06/2026
5.30
Athletic Equipment
01/05/2026
02/06/2026
5.31
Therapeutic Equipment
01/05/2026
02/06/2026
5.32
Stadium Seating
01/05/2026
02/06/2026
5.33
Final Clean
01/05/2026
02/06/2026